    Day 30 Time consuming odds and ends work
    5:24
    Day 27 Master bed outlets, spare bed and bath wiring
    4:38
    Day 28 Easter Sunday, April Fools Day
    6:31
    Day 26 bed and bath light wiring, started laying down sub floor
    9:26
    Day 25 Kitchen, dining wiring, Karen ripped up sub floor
    6:27
    Day 24 Ceiling boxes in, kitchen wiring, water softener drain
    3:59
    Day 23 water softener installed, rain gutters, outlet boxes
    6:10
    Day 22 Removed all useless wire, re-wired the breaker box
    2:52
    Day 21 finished front siding and traced wires
    6:12
    Day 20 foam board and vinyl siding
    4:08
    Day 19 dining room termite damage removed, windows in
    5:24
    Day 18 sill plate and rim joist termite damage repaired
    5:04
    Day 17 backboard by fireplace gone, kitchen windows installed
    2:53
    Day 14, 2 walls up, gutter problems
    8:35
    Day 13 door rough in, attic fan removed
    4:16
    Day 12
    3:54
    Day 11
    4:12
    Day 10
    3:52
    Days 9 Ceiling drywall removed
    5:54
    Day 8
    6:19
    Day 7 all wall drywall gone
    4:18
    Drywall removal bed and bathroom
    4:11